PR PERT Diagram (Angk. 12-A)

Gambarkan PERT Diagram & tentukan jalur kritis untuk kegiatan proyek berikut:

Activity

Preceding Event

Expected Duration

A

2

B

A

3

C

B

4

D

C

5

E

C

4

F

D, E

3

G

F

4

H

F

6

I

G, H

5

J

G

2

K

I, J

4